Basic Question 4 of 29

The net present value of a project is ______.

A. all current revenue minus all current costs
B. the present value of future cash flows minus initial costs
C. the present value of future cash flows netting out those cash flows that occur after the relevant period
D. the present value of future cash flows netting out those cash flows that occur with risk
E. the present value of positive future cash flows

User Contributed Comments 1

User Comment
mattg Initial costs occur @ time period 0 so nominal value = present value
You need to log in first to add your comment.
I passed! I did not get a chance to tell you before the exam - but your site was excellent. I will definitely take it next year for Level II.
Tamara Schultz

Tamara Schultz

Learning Outcome Statements

describe the capital allocation process, calculate net present value (NPV), internal rate of return (IRR), and return on invested capital (ROIC), and contrast their use in capital allocation

CFA® 2025 Level I Curriculum, Volume 2, Module 5.